1.At an iterative planning meeting, new risks were identified. What should agile management professionals do?
- A. Communicate this issue in the next risk management meeting
- B. Record these risks in the risk register
- C. Put these risks on the watch list
- D. Request instructions from management
在一次迭代規劃會上,識別到新的風險。敏捷管理專業人士應該怎么做?
- A、在下一次風險管理會議中溝通這個問題
- B、將這些風險記錄在風險登記冊中
- C、將這些風險放在觀察清單上
- D、請求管理層的指示
2.Provide the agile team with a product to-do to estimate the project size, and the team agrees to use the progressive breakdown method. Which of the following is an advantage of this method?
- A. It takes less time than other estimation techniques
- B. It forces the team to break up larger stories into smaller, more manageable pieces
- C. It is easier to show the speed on the cumulative flow graph
- D. It allows inexperienced team members to participate
向敏捷團隊提供一份產品待辦事項用以估算項目規模,團隊同意使用漸進明細法。下列哪一項屬于這種方法的優點?
- A、它比其他估算技術使用時間要少
- B、它迫使團隊將較大的故事分解成更小、更易于管理的片段
- C、它在累積流圖上更容易顯示速度
- D、它讓經驗不足的團隊成員能夠參與
3.Organizations are going through the transition from waterfall model to agile development. The organization plans to gradually adopt a "hybrid agile" development process. Project managers are hired to lead organizational change and product development. What should they do next?
- A. Establish work authorization and work breakdown structure (WBS)
- B. Avoid micro management and daily management costs
- C. Involve stakeholders and develop processes
- D. Form a small work combination Island
組織正在經歷從瀑布模式到敏捷開發的轉變。該組織計劃逐步采取“混合敏捷”開發過程。項目經理受聘來領導組織轉變和產品開發,其下一步該怎么做?
- A、建立工作授權和工作分解結構(WBS)
- B、避免微觀管理和日常管理費
- C、讓干系人參與,并制定過程
- D、形成小工作組合孤島